The system was used for the internal structure, going up one floor per eight days and making the building ready for roof installation within 10 weeks.  Once this internal structure was erected, external facing bricks were applied and internal fix began at the same time – which cut a 15-month build to around 12 months in total.

 

This was the second time Clearview Homes used Porotherm for the structural internal cavity walls to increase construction speed.  The developer completed a development of 12 houses at Hadley Gate in Alexandra Avenue, also in South Harrow, and shaved two months off the build programme by utilising the system.